[New post] Vogtle nuclear power project – more costs revealed, and even more likely to come.
Christina MacPherson posted: " Georgia Power discloses more Vogtle nuclear delays, big extra costs, By Matt Kempner, The Atlanta Journal-Constitution 30 July 21, Georgia Power's parent, Southern Co., announced Thursday yet another delay in its completion of the nuclear expan"
Georgia Power discloses more Vogtle nuclear delays, big extra costs, By Matt Kempner, The Atlanta Journal-Constitution 30 July 21, Georgia Power's parent, Southern Co., announced Thursday yet another delay in its completion of the nuclear expansion of Plant Vogtle and said its share of the costs have increased by nearly half a billion dollars.
Georgia Power customers could see larger increases in monthly electric bills if the company ultimately seeks reimbursement for the higher costs on the massive project south of Augusta. But such a move would require approval from the state's Public Service Commission.
Southern not only pushed back its timeline for completing the first of two new reactors — something it has done repeatedly this year alone — but also announced a delay for the second reactor. And it cautioned that further delays on both are possible, reeling off a litany of potential challenges to complete a project that was supposed to have been finished years ago and for billions of dollars less.
Another worry: that federal nuclear regulators could continue to increase scrutiny of the project to fix quality problems. The company said in a regulatory filing that "various design and other licensing-based compliance matters" have arisen or may arise that, if not resolved, could lead to additional delays and costs.
As for the latest $460 million in rising costs, the company said it would cover the expense by taking a charge against its profits, a $343 million hit after taxes. The move sparked lower profits for Southern compared to the same quarter a year earlier. The company didn't say whether it eventually will seek approval from state regulators to recover those costs from its customers. But in a filing it said there is a "significant level of uncertainty" about its ability to get such a full recovery...........
Just a few months ago, Atlanta-based Southern had been sticking by its predictions that the first reactor would be in operation this November, with the second a year later. Now, it projects the second quarter of 2022 for the first, and the first three months of 2023 for the last reactor. In each case that is three or four months later than what it had said in May and reasserted again last month.
The two new reactors were originally slated to be in operation in 2016 and 2017, respectively..........
Kurt Ebersbach, a senior attorney at the Southern Environmental Law Center, which represents some organizations opposed to customers paying for Vogtle's excesses, said he believes the power company will seek PSC approval to collect billions of dollars in overruns from customers.
The construction costs of the Vogtle expansion have not yet been rolled into the bills of Georgia Power customers. But for years, customers have paid fees for a portion of both the project's financing costs and the company's profits on it.